Work orders - the standard and automatic entry of material and work consumption

Updated 28.11.2024

The standard that determines the products planned for consumption during fulfillment can be created for the product.



When selecting the product with standard, for the material and work planned, all products from standard should be added.



When entering the quantity of the planned ordered product, the realized quantity can also be entered. If consumption/realization for materials and work is not specified, it will be automatically added based on the appropriate proportions at the end. 




After completing the work order, the consumption of all material added to the work order will be automatically processed, regardless of whether the material was added to the work order using standard or manually.





Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article